Wednesday, December 19, 2007

Floor Plan for SDNA Building

Here is a quick look at what the exterior of the building will look like, as well as the floor plan. Click on the image for a better view of the plan. While the snow in December slowed construction for now, the contractor was very pleased about how far the project progressed before the weather turned cold. All concrete work on the foundation, basement and parking lot was completed this fall. Plus, the first layer of asphalt was put down on the parking lot, allowing it to settle properly through the winter months. Look for framework on the building to get underway soon.

Sunday, November 25, 2007

Work Progresses on Building



There has been considerable work at the building site the past few weeks. And it's all work that the contractor wanted to complete before the weather turned really cold. The curb and gutter and sidewalks are completed. The first layer of asphalt has been put on the parking lot. A floor covers the basement portion of the building. Now construction can start on the building frame.

Sunday, November 11, 2007

Work on Curb, Sidewalk



Last week the curb for the parking lot and the sidewalk on the front side of the building were completed.

Tuesday, November 6, 2007

Ground Floor Concrete Poured


Last Saturday, Nov. 3, the concrete for the ground floor was poured. This view is from the parking lot near approximately the southeast corner of the building.

Monday, November 5, 2007

Basement Floor Poured


A basement to be used for storage and utilities will be under the west half of the building. The floor was poured two weeks ago once sewer and water lines were put in place. This view is from the south side of the building looking toward the northwest corner of the building.

Parking Lot Work


Work started last week on grading the parking lot. The plan is to have the curb and gutter for the entrance off the street and the parking lot completed before the season turns too cold. This view is looking west from 32nd Ave. toward the entrance to our lot.

Monday, October 8, 2007

Foundation Work Continues


This past week workers poured the footings and set the forms for the foundation and the basement walls. Rain over the weekend halted work until the site can dry out.