Sunday, November 25, 2007
Work Progresses on Building
There has been considerable work at the building site the past few weeks. And it's all work that the contractor wanted to complete before the weather turned really cold. The curb and gutter and sidewalks are completed. The first layer of asphalt has been put on the parking lot. A floor covers the basement portion of the building. Now construction can start on the building frame.
Sunday, November 11, 2007
Work on Curb, Sidewalk
Tuesday, November 6, 2007
Ground Floor Concrete Poured
Monday, November 5, 2007
Basement Floor Poured
Parking Lot Work